What home elevator installation involves, step by step
A home elevator project runs in seven stages, and the elevator itself is installed near the end: most of the time goes to design, permits, factory production and preparing the space.117
- Home visit and assessment. A dealer looks at where an elevator could go on every floor, ceiling heights, load-bearing walls and how the floors connect.17 Space that lines up on each floor, such as stacked closets, makes the project much simpler.19 If the rider has a disability, an occupational therapist can advise on cab size and door type.
- Choose the type and design. Shafted (hydraulic, chain or inline gear, traction, winding drum), pneumatic vacuum or through-floor; then cab size, doors and finishes. Types are compared in our home elevator guide.17
- Drawings, quote and permit. The dealer supplies a quote and job-specific drawings that your builder works from and that are usually submitted for the permit.1 Permits can take 2 to 4 weeks.19
- Factory production. After you sign off on drawings and price, the elevator is built: about 4 to 5 weeks at one manufacturer, 10 to 12 weeks for highly custom elevators.1
- Prepare the space. Your general contractor builds the shaft, pit, reinforced rail wall, landing door openings and any machine room, and an electrician runs the circuits.1 HomeGuide puts this at 4 to 5 weeks for a traditional elevator and 1 to 3 weeks for a shaftless one.18
- Install and test. The dealer's crew sets the rails, drive, car, controls and call stations, then tests every safety device.171
- Inspection and handover. Where required, an inspector checks the installation and its tests before first use; the dealer then shows you how to use it, what to do in a power cut, and the maintenance schedule.4117
For through-floor and pneumatic vacuum elevators, step 5 is much smaller: there is no shaft or pit, just a floor or ceiling opening and wiring.201817 What each stage costs is on our home elevator cost page.
Who does what: dealer, contractor, electrician and inspector
The elevator dealer installs the elevator, but the shaft is usually your general contractor's job, built to the dealer's drawings, so you need both lined up before work starts.1
| Who | Usually responsible for |
|---|---|
| Elevator dealer or installer | Site assessment, design, drawings, ordering, delivery, installing and testing the elevator, often the permit application and booking the inspection, handover and maintenance.117 |
| General contractor or builder | Shaft framing and drywall, pit, reinforced rail wall, landing door openings, machine room if needed, patching and flooring. Savaria says "your general contractor is responsible for constructing and preparing the hoistway."1 |
| Licensed electrician | Dedicated circuits, lockable disconnects and any panel upgrade, to the maker's specification.14 |
| Inspector | Where required, a state, city or licensed third-party inspector checks the installation before first use (for example, a state inspector in Georgia; the Department of Labor & Industries in Washington).413 |
| You | Choosing the location, approving drawings, a phone line for the in-car phone, clearing the work area, and keeping up maintenance.1 |
Space, pit, overhead, electrical and phone requirements
A typical shafted home elevator needs about 25 square feet (5 by 5 feet) on every floor, a pit of about 6 to 10 inches below the lowest floor, about 92 to 108 inches of overhead above the top floor, two dedicated circuits and a phone connection.12 Exact figures depend on the model, so treat these as planning numbers until you have the maker's drawings.
| Requirement | Typical figure | Basis |
|---|---|---|
| Footprint on each floor | About 5 × 5 ft (25 sq ft); about 4 × 4 ft with a smaller cab | Savaria planning guide1 |
| Cab (car) size | Up to 15 sq ft inside; up to 18 sq ft where the local authority approves | ASME A17.1-2013 5.3.1.10 (state summaries); Savaria and Cibes on 18 sq ft3412 |
| Pit depth | 6 minimum, 8 preferred (Cibes); 8 to 10 with a poured concrete floor (Savaria) | Manufacturer guides21 |
| Overhead (top floor to shaft ceiling) | About 92 to 96 minimum (Savaria); 94 hydraulic, 96 to 108 inline gear for a 7-ft cab (Cibes) | Manufacturer guides12 |
| Clearance above the car | 6 minimum, rising to 9 at 40 ft per minute | ASME A17.1-2013 5.3.1.3 (state summaries)34 |
| Rail wall | One wall reinforced to carry the rails, square and plumb within 1/8 in; no unrelated pipes, ducts or sprinklers in the shaft | Cibes; ASME 5.3.1.5 summary23 |
| Machine room | Hydraulic: a closet-size room (4 × 5 ft for one model), pump within 40 ft of the cylinder, 50 to 80 °F. Machine-room-less: controller in a mechanical room or closet. | Savaria; Cibes12 |
| Electrical | A dedicated 208/230-volt circuit for the drive (20 A inline gear, 30 A hydraulic in one guide) and a 120-volt, 15 A circuit; lockable disconnects; drive breaker not GFCI; 30 × 36 in clear in front of the controller | Cibes; Savaria; Georgia checklist (NEC 620)214 |
| Phone and alarm | A phone in the car and an alarm audible outside the shaft; a landline or the maker's cellular option | ASME 5.3.1.19 summary; Savaria31 |
| Landing doors | A door with an interlock at every floor; 4 in max door to car gate and 3/4 in max door to sill for swinging doors (2016 rule) | ASME A17.1-2016 as summarized by New Jersey and CPSC staff; Savaria; Cibes; see the door-gap section9812 |
| Power failure | A manual or battery lowering means; Savaria's lowers the car to a landing below | ASME 5.3.1.16 summary; Savaria31 |
Shaftless types are different. Pneumatic vacuum and through-floor lifts need no pit or shaft; one pneumatic maker's smallest model needs a 32-inch floor opening.20 Space and ceiling needs for those are covered in through-floor elevators and pneumatic vacuum elevators. Garage stops may need a weather-sealed or fire-rated door, and home elevators must run inside the house.1
What the safety code limits for home elevators
Home elevators in the US and Canada are built to ASME A17.1/CSA B44, Section 5.3 (private residence elevators), which caps speed at 40 feet per minute and travel at 50 feet, and limits the car to 15 square feet in the 2013 edition.13 The current edition is 2025, but each state adopts editions on its own schedule, so your inspector may enforce an older one.52
| Item | Limit |
|---|---|
| Rated speed | 40 feet per minute maximum3 |
| Rise (travel) | 50 feet maximum3 |
| Inside platform area | 15 square feet maximum34 |
| Capacity | At least 40 lb per sq ft or 350 lb, whichever is more, for platforms up to 12 sq ft; at least 62.5 lb per sq ft above 12 sq ft3 |
| Car gate | Required on every car entrance, electrically monitored so the car can't move unless the gate is within 2 inches of closed3 |
| Hoistway doors | Locked by a listed interlock; car can't move unless the door is closed and locked; must withstand 150 pounds of force34 |
| Use | Only in a private residence, not accessible to the public41 |
Some limits changed in later editions. The door rule is the important one: the 2016 edition tightened the gap between the landing door and the car gate, and Savaria says the 2016 door rules must be met even where a state still follows an older edition.12 Platform lifts and stair lifts follow a different standard, ASME A18.1;11 see wheelchair lifts for home.
The door gap that can trap children, and the 4-inch rule
Young children can be crushed in the space between a home elevator's landing door and the car's inner gate, so no gap there should be deeper than four inches.67 If a child can step into that space and close the landing door behind them, the elevator can be called to another floor with the child trapped between the doors.6 CPSC says residential elevators were linked to 4,600 injuries and 22 deaths from 1981 through 2019.7
Safety warning from the U.S. Consumer Product Safety Commission
CPSC says to make sure the gap between the doors is no more than four inches deep; if you are unsure, lock the elevator in an unusable position or lock all the landing doors, and contact the manufacturer or an elevator installer for space guards or an electronic monitoring device.67 On January 11, 2022, Bella Elevator, Inclinator and Savaria agreed to recalls to fix hazardous gaps, and CPSC warned owners of Waupaca residential elevators to lock them until they were inspected; CPSC says three children were trapped in other makers' home elevators in summer 2021 and a 7-year-old was killed in a vacation home.12 Savaria's recall covers about 19,500 Savaria and Garaventa elevators, with space guards provided free.10 Installers should never leave a gap deeper than four inches, measured in accordance with ASME A17.1-2016.7
- The 2016 rule: no more than 4 inches from the hoistway face of the landing door to the car door or gate, checked with a 4-inch ball, and no more than 3/4 inch from the inside of a swinging landing door to the edge of the sill (2.25 inches for sliding doors), often called the "3/4-inch by 4-inch rule."891 Cibes's planning guide says the door-to-sill limit drops to 1/4 inch when the car has an accordion door, and that these limits apply to the 2016 and newer editions.2
- Older rule: the 2013 edition allowed up to 3 inches from door to sill and 5 inches from door to gate; CPSC staff say the 2016 change to 4 inches addresses that hazardous 5-inch dimension.38 Georgia and Massachusetts allow only 3 inches from door to gate.24
- Existing elevators: CPSC refers owners to ASME A17.3-2017, the code for existing elevators, and to a qualified inspector.12
- At handover: ask the installer to measure each landing in front of you, especially if your builder supplied the landing doors.1
How long it takes to install a home elevator
The installation crew is usually in your home for 1 to 8 working days depending on type, but the whole project takes weeks to months because of design, permits, factory production and construction.17118
| Type | On-site installation | Preparation before the crew arrives (existing home) |
|---|---|---|
| Through-floor (shaftless) | 1 to 2 days17 | 1 to 3 weeks18 |
| Pneumatic vacuum | 1 to 3 days (the maker says 2 to 3)1720 | Minimal; no shaft or pit20 |
| Inline gear (no machine room) | 3 to 5 days17 | 4 to 5 weeks for the shaft18 |
| Hydraulic | 4 to 7 days or more17 | 4 to 5 weeks for the shaft and machine room18 |
| Any shafted model (one maker) | 4 to 8 working days1 | Builder-dependent |
Before the crew arrives, add time for permits (2 to 4 weeks) and factory production (4 to 5 weeks, longer for custom work).191 In new construction the elevator usually goes in near the end, typically just after flooring, so the order has to be placed weeks ahead.17
Plan your installation: requirements and timeline
The planner turns your answers into a checklist of what your house needs and a rough schedule in the order the work happens. It doesn't replace a site visit; it helps you ask the right questions.
Home elevator installation planner
PlannerFirst visit to first ride
9 to 16 weeks
Work on site
4 to 7 working days
Permit
Find out first
Your step-by-step timeline and checklist appear here when JavaScript is on. The worked example below shows the same method.
How it works: production of the elevator starts after you approve drawings and price, and runs while the permit is reviewed and your contractor prepares the space; installation starts when both are done. Published durations: factory production 4 to 5 weeks, or 10 to 12 for highly custom elevators (Savaria); permits 2 to 4 weeks (Lifeway Mobility); construction prep 4 to 5 weeks for a shafted elevator or 1 to 3 weeks for a shaftless one (HomeGuide); on-site installation from 1 to 2 days for a through-floor lift to 3 to 8 working days for a shafted elevator (HomeLift, Savaria). Our own planning assumptions, not published figures: 1 to 3 weeks for consultation and quotes, and 1 to 2 weeks to schedule an inspection. Requirements are typical planning figures from manufacturer guides and the code summaries cited on this page; your installer's job-specific drawings and your local inspector decide.
Worked example. A two-stop hydraulic elevator in an existing home, permit status unknown, standard model. Consultation and quote: 1 to 3 weeks (our assumption). Production, 4 to 5 weeks, starts at sign-off and runs while the permit (2 to 4 weeks) is reviewed and the shaft (4 to 5 weeks) is built, so the longer path is permit plus shaft: 6 to 9 weeks. Installation: 4 to 7 working days, about 1 to 1.5 weeks. Inspection: 1 to 2 weeks (our assumption). Total: 1 + 6 + 0.8 + 1 ≈ 9 weeks at the short end and 3 + 9 + 1.4 + 2 = 15.4, rounded up to 16 weeks at the long end.1191817 The same home with a through-floor lift comes to about 7 to 13 weeks, almost all of it production and permits.
Permits and inspection: who inspects in your state
Most home elevators need a building permit, and many states also require a state inspection before first use, but there is no single national rule: some states inspect every new home elevator, and others leave homes to local building departments.141315 Three real examples:
| State | What the state's rules say |
|---|---|
| Georgia | Anyone installing, altering or maintaining residential elevators must hold a Certificate of Authorization from the state's Safety Engineering Division; new equipment must be permitted before installation and inspected by a state inspector before use. Georgia also sets a 3-inch limit from landing door to car door.4 |
| Washington | The Department of Labor & Industries inspects all new, altered or relocated elevators in single-family homes; a licensed elevator contractor files the permit before installation. No annual inspection is required unless the owner asks for one. A license is required to install, alter or repair a home elevator.1314 |
| Texas | The state elevator program lists equipment in a private residence as an exempt location for its plan review. Ask your city or county building department what permit and inspection it requires.15 |
Elsewhere, start with your city or county building department and ask whether your state has an elevator safety office. A dealer that works in your area should know the local process; HomeLift notes that permit and inspection requirements can vary by county and municipality.17 Who pays for the inspection and permit, and what they cost, is on the cost page.
How to find and check home elevator installers near you
Home elevators are usually sold and installed by authorized dealers of each manufacturer, so the practical way to find installers near you is to choose two or three makers that fit your house and contact their local dealers, then check each one's license, credentials and insurance.1220
- Use manufacturers' dealer locators. Savaria says its local dealer installs the elevator; Cibes sells through a network of authorized dealers; PVE connects buyers with an authorized installer.1220 Our comparison of home elevator companies lists makers by type.
- Check the license where your state requires one. Washington requires a license to install a home elevator and Georgia requires a Certificate of Authorization; ask your state agency how to look one up.144
- Ask about technician certification. The National Association of Elevator Contractors certifies Certified Elevator Technicians (CET) and Certified Accessibility and Private Residence Lift Technicians (CAT). HomeGuide also suggests asking whether installers trained through the National Elevator Industry Educational Program (NEIEP). These are industry credentials, not a substitute for a state license.1618
- Ask for proof of insurance and whether they are licensed, bonded and insured.18
- Ask who inspects. Where the state doesn't inspect, a Qualified Elevator Inspector (QEI; NAEC is one body that certifies them) can check the installation; CPSC points owners to an inspector search.1612
- Get more than one written quote and never pay in full until the elevator has passed every required inspection.18
You can also use the request form on this page: give your ZIP code and a person passes your request to no more than two installers or manufacturers that serve your area. We don't install elevators or have local offices.
Questions to ask a home elevator installer
Ask these in writing and keep the answers with your contract.
- Are you licensed for elevator work in this state, and can I see the license, your insurance certificate and your technicians' certifications?14416
- Which models fit my space, and why this one? What are its pit, overhead and footprint needs?1
- Who builds the shaft, pit and rail wall, and will you visit to check the construction before installation?1
- What electrical work is needed, and does my panel have room?218
- Who applies for the permit and books the inspection, and which code edition does our inspector enforce?15
- Will every landing meet the 3/4-inch and 4-inch door rule, and will you measure each one at handover?17
- What are the production lead time and on-site installation time?1
- How does emergency lowering work in a power cut, and how does the in-car phone connect?1
- What does the warranty cover and for how long? (One maker's standard is a three-year limited parts warranty.)2
- What does a maintenance plan cost, and how quickly do you respond to a breakdown?
- What is the payment schedule, and is the final payment due after inspection?18
How to compare installation quotes line by line
Compare quotes item by item, not by the bottom line, because one quote may include the shaft, permit or doors and another may leave them to you. PVE, for example, recommends itemized quotes that separate equipment, installation labor, shaft or pit construction, electrical upgrades, permits, finishes and options.20
| Line | What to check |
|---|---|
| Model and drive | Exact model, drive type, rated capacity, cab size, speed |
| Stops and travel | Number of stops, total travel, door positions at each floor |
| Gates and landing doors | Gate type, who supplies landing doors, compliance with the 2016 door rule, automatic operation if needed |
| Installation labor | Included, crew size, days on site, travel charges for remote homes |
| Shaft, pit, rail wall | Included or by your contractor; if excluded, the drawings and a site check before install |
| Machine room or controller space | Location, size, temperature needs |
| Electrical | Circuits, disconnects, panel work: included or by your electrician |
| Phone | Phone hardware included; landline or cellular service needed |
| Permit and inspection | Who applies, who pays the fees, who attends the inspection |
| Finishes and flooring | Cab walls, ceiling, lighting, flooring (often by your contractor) |
| Taxes, shipping, disposal | Included or extra |
| Warranty | Parts and labor, length, what voids it |
| Maintenance | First-year service, annual plan price, response times |
| Schedule and payments | Lead time, install dates, deposit, final payment after inspection |
Price ranges for each of these lines, and an estimator that adds them up, are on the home elevator cost page. If an elevator turns out not to fit, a platform lift or a stair lift may; see stair lift prices.
Limits of this guide
What this page can and can't tell you
Requirements here are typical planning figures from two manufacturers' guides and from state summaries of the 2013 edition of ASME A17.1 Section 5.3, with the 2016 door rule as described by CPSC staff and New Jersey's elevator unit; we have not read the purchased 2025 code, and states enforce different editions. Timelines are published figures from manufacturers, a dealer and a cost guide, combined with two planning assumptions that we label as ours. State examples cover three states only. Your installer's job-specific drawings, your local building department and your inspector decide what your home needs. This site is a consumer guide and referral service: we don't sell, install, inspect or service elevators, and naming a company is not a recommendation.
Request installers who serve your ZIP code
If you'd like installers to contact you, the form on this page goes to a person who reads it and shares it with no more than two installers or manufacturers that serve your ZIP code. They contact you directly; you decide whether to hire anyone. Companies that receive requests may pay us a referral fee, explained in our referral disclosure and on how it works. It helps to include the number of floors, whether the home is existing or new, the elevator type you're considering, and who will ride.
Sources
- Ultimate Guide to Home Elevators, Savaria (manufacturer), updated October 20, 2026. Space, pit, overhead, machine room, circuits, phone, door rule, who builds the hoistway, production lead time, installation days, inspection and turnover. Checked 2026-11-27.
- Home Elevator Design Guide (ASME A17.1, Section 5.3), Cibes Symmetry (manufacturer), 2026. Planning figures for pit, overhead, power supply, controller space, rail backing, door gap limits by code edition and state. Planning only, not for construction. Checked 2026-11-27.
- ASME A17.1-2013 Section 5.3 Private Residence Elevators, Synopsis, Montana Department of Labor and Industry, Building Standards (synopsis prepared from a manufacturer's installer notes). Summary of 5.3 requirements: clearances, hoistway doors, car enclosure and gate, capacity, speed, rise, phone, manual lowering. Not the full code. Checked 2026-11-27.
- Frequently Encountered Items Which Delay Acceptance of New Residential Elevators, Georgia Office of Commissioner of Insurance and Safety Fire, Safety Engineering Division, March 2019. Inspection checklist; installer authorization, permit and inspection before use; door and car clearances; electrical disconnects. Checked 2026-11-27.
- A17.1, Safety Code for Elevators and Escalators, ASME, 2025 edition current. Editions listed: 2007, 2010, 2013, 2016, 2019, 2022, 2025. The code text is sold, not free. Checked 2026-11-27.
- CPSC Alert: Protect Children from a Deadly Gap between Doors of Home Elevators, U.S. Consumer Product Safety Commission, 2019. Four-inch gap limit; lock the elevator if unsure; space guards or electronic monitoring. Checked 2026-11-27.
- Vacation Rental Homes Can Pose a Deadly Hazard: Kids Can Be Crushed to Death in Dangerous Home Elevator Gaps, U.S. Consumer Product Safety Commission, 2021. Gap measured in accordance with ASME A17.1-2016. Checked 2026-11-27.
- Staff Briefing Package: Petition CP 15-1 Requesting Rulemaking on Residential Elevators, U.S. Consumer Product Safety Commission staff. Quotes ASME A17.1-2013 5.3.1.7.2 (3 in door to sill, 5 in door to car gate) and describes the 2016 edition: 4 in maximum, checked with a 4 in diameter ball, plus a rigidity test for folding car doors. Checked 2026-11-27.
- Construction Code Communicator, Summer 2020: Private Residence Elevator Hoistway Door Clearances, New Jersey Department of Community Affairs, Division of Codes and Standards, Summer 2020. Under ASME A17.1-2016: 0.75 in maximum from hoistway door to sill edge for swinging doors, 2.25 in for sliding doors; 4 in maximum from hoistway door face to car door or gate for all door types. Checked 2026-11-27.
- Residential Elevators Recalled by Savaria Corporation Due to Child Entrapment Hazard, U.S. Consumer Product Safety Commission, January 11, 2022 (recall 22-047). About 19,500 Savaria and Garaventa residential elevators; space guards free of charge, installation help on request; no incidents reported. Checked 2026-11-27.
- A18.1, Safety Standard for Platform Lifts and Stairway Chairlifts, ASME, 2023 edition listed. The standard for platform lifts and stairway chairlifts, separate from A17.1. Checked 2026-11-27.
- CPSC Urgent Warning: Stop Using Waupaca Residential Elevators Due to Fatal Entrapment and Serious Fall Hazards, U.S. Consumer Product Safety Commission, January 11, 2022 (warning 22-049). Recalls by Bella Elevator, Inclinator and Savaria; 2021 incidents; ASME A17.3-2017 for existing elevators; inspector search. Checked 2026-11-27.
- WAC 296-96-01045, Residential elevator inspections, Washington State Legislature, effective November 1, 2025. State inspection of new, altered or relocated single-family conveyances; permit by a licensed contractor before installation; no annual inspection unless requested. Checked 2026-11-27.
- Building Owners & Property Managers (Elevator Program), Washington State Department of Labor & Industries. A license is required to install, alter or repair a private residential conveyance. Checked 2026-11-27.
- Elevator Safety and Licensing Frequently Asked Questions, Texas Department of Licensing and Regulation. Equipment in a private residence is listed as an exempt location for department plan review. Checked 2026-11-27.
- Certification (CET, CAT and QEI programs), National Association of Elevator Contractors. Certified Elevator Technician; Certified Accessibility and Private Residence Lift Technician; Qualified Elevator Inspector. Checked 2026-11-27.
- What to Expect During a Home Elevator Installation Step by Step, HomeLift (dealer, Tennessee and Alabama), updated November 24, 2026. Installation days by type; elevator installed near the end of new construction; third-party inspection. Checked 2026-11-27.
- How much does a home elevator cost?, HomeGuide, written October 25, 2023. Installation and preparation durations; tips for hiring installers; door width for wheelchairs. Checked 2026-11-27.
- Home Elevator Installation: What to Expect, Lifeway Mobility (dealer and installer, select states). Permits can take 2 to 4 weeks; stacked closets; automatic doors for wheelchair access. Checked 2026-11-27.
- Home Elevator Cost Guide 2026: Prices & Key Factors, PVE, Pneumatic Vacuum Elevators (manufacturer), revised November 26, 2026. No pit, shaft or machine room for its models; 2 to 3 day installs; 32-inch opening for its smallest model; itemized quotes. Checked 2026-11-27.